This Tech Doc shows how to finalise the installation on the Haulotte HA16PE/HA18PX Boom Lift
Installation Steps:
1. Place the lid back onto the operator control box and tighten the 4 bolts that secure the lid.


2. Connect the M23 connector from the Control Module to the socket installed in the operator control box.
3. Make sure that the connector is screwed up finger tight.


4. Inspect the entire Crush Guard installation, make sure that all bolts, connectors and cables are secure.
5. Make sure that the machine is fit for operation. 

    • Related Articles

    • Crush Guard - Installation - Haulotte Star10 Finalisation

      This Tech Doc shows how to finalise and complete the installation Installation Steps: 1. Place the lid back onto the operator control box and tighten the 4 bolts that secure the lid. 2. Connect the M23 connector from the Control Module to the socket ...
    • Crush Guard - Installation - Genie ALC500/ALC1000 Finalisation

      This Tech Doc outlines the finalisation stages Finalisation Steps: 1. Place the lid back onto the operator control box and tighten the 4 bolts that secure the lid. 2. Connect the M23 connector from the control module to the socket installed in the ...
    • Crush Guard - Installation - Manitou 160ATJ/180ATJ/200ATJ Finalisation

      This Tech Doc shows the Finalisation steps on the Manitou 160ATJ/180ATJ/200ATJ Boom Lift Finalisation Steps: 1. Connect the M23 connector from the Control Module to the socket installed in the operator control box. 2. Make sure that the connector is ...
    • Crush Guard - Installation - Haulotte Star10 Crush Guard Frame Installation

      This Tech Doc shows how the Crush Guard frame is Installed on the Man Platform Installation Steps: 1. Position the Crush Guard Frame on the man platform. 2. Secure the frame to the horizontal posts on each side of the operator controls using the ...
    • Crush Guard - Installation - JLG X19J Finalisation

      This Tech Doc shows how to Finalise and complete the installation Installation Steps: 1. Replace the lid to the electronic enclosure. 2. Connect the M23 connector from the control module to the socket installed in the operator control box. 3. Make ...