Crush Guard - Installation - Manitou 160ATJ/180ATJ/200ATJ Finalisation

Crush Guard - Installation - Manitou 160ATJ/180ATJ/200ATJ Finalisation

Notes
This Tech Doc shows the Finalisation steps on the Manitou 160ATJ/180ATJ/200ATJ Boom Lift
Finalisation Steps:
1. Connect the M23 connector from the Control Module to the socket installed in the operator control box.
2. Make sure that the connector is screwed up finger tight.
3. Secure the M23 connector cable to the EWP frame using cable ties.


4. Inspect the entire Crush Guard installation
5. Make sure that all bolts, connectors and cables are secure.
6. Make sure that the machine is fit for operation.