SFPL - Installation - GMJ LL28-300 Display Housing

SFPL - Installation - GMJ LL28-300 Display Housing

The display is housed within a IP67 rated enclosure and must be installed on the left side of the LL28-300 turret.
The unit must be secured using four M6 bolts in each corner of the housing. 



    • Related Articles

    • SFPL - Installation - Generic Display Housing, Cable Reeler & Light Tower Installation

      Display Installation The display is housed within a IP67 rated enclosure and must be installed on the left side of the turret. The unit must be secured using four M6 bolts in each corner of the housing. Cable Reeler Installation The cable reeler is ...
    • SFPL - Installation - GMJ LL28-300 - Light Tower

      The light tower should be mounted in a location visible to workers around the man platform. Secure using four M6 bolts. Run the cable to the display housing and connect to the spare M12 female connector. The light tower can be connected into either ...
    • SFPL - Installation - GMJ LL28-300 - Cable Reeler Installation

      The cable reeler is designed to mounting inside the boom. Secure the cable reeler with the nylon cable running out the top pointing towards the inside of the boom, mount using four M8 bolts in each corner. Extend the nylon cable and anchor it to the ...
    • SFPL - Installation - GMJ LL28-300 - Power / Cutout

      The system uses a 4-Pin cable to supply power to the system and to signal cutout / fault conditions. Connect the supplied 4-Pin cable to the left male connector on the display. Connect the other end of the cable according to the table below. The ...
    • SFPL - Installation - Sensor Calibration

      Once the installation is complete, the sensors will require calibration. Sensors may also require re-calibration with other maintenance tasks (Display, SD card, Cable reeler replacement) Sensor calibration steps below: A sensor calibration must be ...