The hydraulic pressure sensors are used to measure the lifting load of the ITC
Main Cylinder
1. Completely lower the boom. Apply
the handbrake and insert chock
under wheels.
Once lowered, release any residual
pressure by pulling on the manual
release valve.
2. The Head End pressure sensor is
installed inline with the Head
hydraulic line on the left hand main
lift cylinder. The sensor is installed
using the supplied sandwich plate.
3. Remove the existing the rod end line
from the connection point.
4. Install the manifold block
(HY001103) in series and apply the
new longer bolts M12 x 70mm.
Tighten the bolts for the hose to 41
Nm using a torque wrench.
Make sure the sensor is positioned
facing
5. The Rod End pressure sensor is
installed in the location shown in the
diagram.
6. Connect the supplied M12 4 metre
cables (CB001026) into each of the
pressure sensors.
Cable tie to the flexible hydraulic
hoses nearest to the sensors. Make
sure the cable isn't pinched or
stretched when the boom is raised
or lowered.
Pressure Manifold Components
Main Rod Pressure Sensor Manifold Components
Main Head Pressure Sensor Manifold Components

Failure to tighten the bolts to the correct torque on the
pressure manifold may result in a pressure failure on the
counterbalance valve causing an uncontrolled fall of the boom.