Gen3_ITC - Installation - Volvo L120H Man Platform Cameras Installation

The Man Platform camera’s are displayed on the screen when the Man Platform is
connected.
Installation Steps:
1. Feed approximately 2m of the cable
with the 6 pin connector side from
the outside through the cabin entry
grommet.
2. Route the cable along the path
shown in the diagram to prevent
tension on cable during movement of
front end during steering.
3. Route cable along existing hosing,
up to the front of the machine
securing with cable ties.

The camera's viewing angle may need to be adjusted once the
system is installed and the display is operational.

Do not disconnect the camera power connection while the
system is operating as this can damage the fuse.
Related Articles
Gen3_ITC - Installation - Volvo L120H Main Head & Rod Pressure Sensors
The hydraulic pressure sensors are used to measure the lifting load of the ITC Installation Steps: Completely lower the boom. Apply the handbrake and insert chock under wheels. Once lowered, release any residual pressure by pulling on the manual ...
Gen1 - User - Man Platform Operations
When the man platform has been attached to the telehandler, the range of movement is limited to 3 meters height and 5 meters radius while the stabilizers are up. If these limits are exceeded the cutout will engage. The cutout generated for a man ...
Gen3_ITC - General - What is a GEN 3 ITC?
This system has been designed specifically for use with Integrated Tool Carriers (ITC) to cover all relative national and international safety standards. This Tech Doc details system specifications, system functionality, installation requirements, ...
Gen3_ITC - Installation - Volvo L120H Display Installation
The display shows the current safety status of the ITC. Installation Steps: Position the display bracket at the top left of the Switch Column. Drill two M6 holes to attach the bracket to the Switch Column. Secure the bracket to the switch column ...
Gen3_ITC - Installation - Volvo L120H Articulation Sensor Installation
The articulation sensor is mounted mid machine at the point of machine articulation Installation Steps: 1. Drill two M6 holes for the Articulation base plate in the location shown, using the plate as a guide to mark the M6 hole locations. Make sure ...