Gen3_ITC - Installation - Caterpillar 962K Installation Finalisation
This Tech Doc will complete the final power connections to power the system and finish any
additional items
Installation Steps:
1. Connect the 3 pin connector from
the “24V to 12V converter” to the
power/camera harness. And make
sure that the 24V to 12V
converter power switch is set to
ON.
2. Connect the 6 Pin connector from
the ‘machine cutout’ harness to
the IO harness.
3. Connect the spade lug on the
black wire to the negative (black)
battery terminal then connect the spade lug on the blue
wire to the positive (red) battery
terminal.
4. Slide the CCIM back into it’s
designated position and then
fasten the 24V to 12V converter
in the position shown in the
diagram using the supplied Velcro
strips.
5. De-activate the battery isolation.
Turn the machine onto first
stage /accessories and ensure the
system is activated.
6. Adjust the display bracket for
optimal viewing
Set the machine into reverse gear
to activate the reverse camera.
Adjust the reverse camera so the
video is level.
7. Perform a final check on all the
cabling and sensors.
Replace all the covers

Some machines had wiring modifications applied by the end user and may not match the wiring in this Tech Doc

Complete the system checklist once installation has been
completed
Related Articles
Gen3_ITC - Installation - Caterpillar 962K Display Installation
The display shows the current safety status of the ITC Installation Steps: Position the display bracket at the top left of the Switch Column. Drill two M6 holes to attach the bracket to the Switch Column. Secure the bracket to the switch column using ...
Gen3_ITC - Installation - Caterpillar 962K Signal Light Installation
The signal light warns other workers when the ITC is lifting loads close to it's maximum capacity Installation Steps: 1. Drill and tap four M4 holes to mount the signal light bracket to the left side of the cabin roof (location shown in the photo). ...
Gen3_ITC - Installation - Caterpillar 962K Pressure Sensor Installation
The hydraulic pressure sensors are used to measure the lifting load of the ITC Main Cylinder Installation Steps: 1. Raise the boom to approximately 40 degrees. Support and secure the boom using an A Frame or similar apparatus. It must support at ...
Gen3_ITC - Installation - Volvo L120H & L90 Installation Finalisation
This Tech Doc will complete the final power connections to power the system and finish any additional items Installation Steps: 1. Connect the 3 pin connector from the “24V to 12V converter” to the power/camera harness. Make sure that the 24V to 12V ...
Gen3_ITC - General - What is a GEN 3 ITC?
This system has been designed specifically for use with Integrated Tool Carriers (ITC) to cover all relative national and international safety standards. This Tech Doc details system specifications, system functionality, installation requirements, ...