This Tech Doc will complete the final power connections to power the system and finish any additional items
Installation Steps:
1. Connect the 3 pin connector from the “24V to 12V converter” to the power/camera harness. And make sure that the 24V to 12V converter power switch is set to ON.


2.  Connect the 6 Pin connector from the ‘machine cutout’ harness to the IO harness.


3. Connect the spade lug on the black wire to the negative (black) battery terminal then connect the spade lug on the blue wire to the positive (red) battery terminal.


4. Slide the CCIM back into it’s designated position and then fasten the 24V to 12V converter in the position shown in the diagram using the supplied Velcro strips.


5. De-activate the battery isolation. Turn the machine onto first stage /accessories and ensure the system is activated.


6. Adjust the display bracket for optimal viewing Set the machine into reverse gear to activate the reverse camera. Adjust the reverse camera so the video is level.


7. Perform a final check on all the cabling and sensors. Replace all the covers

Notes
Some machines had wiring modifications applied by the end user and may not match the wiring in this Tech Doc
Alert
Complete the system checklist once installation has been completed 
    • Related Articles

    • Gen3_ITC - Installation - Caterpillar 962K Display Installation

      The display shows the current safety status of the ITC Installation Steps: Position the display bracket at the top left of the Switch Column. Drill two M6 holes to attach the bracket to the Switch Column. Secure the bracket to the switch column using ...
    • Gen3_ITC - Installation - Caterpillar 962K Signal Light Installation

      The signal light warns other workers when the ITC is lifting loads close to it's maximum capacity Installation Steps: 1. Drill and tap four M4 holes to mount the signal light bracket to the left side of the cabin roof (location shown in the photo). ...
    • Gen3_ITC - Installation - Caterpillar 962K Pressure Sensor Installation

      The hydraulic pressure sensors are used to measure the lifting load of the ITC Main Cylinder Installation Steps: 1. Raise the boom to approximately 40 degrees. Support and secure the boom using an A Frame or similar apparatus. It must support at ...
    • Gen3_ITC - Installation - Volvo L120H & L90 Installation Finalisation

      This Tech Doc will complete the final power connections to power the system and finish any additional items Installation Steps: 1. Connect the 3 pin connector from the “24V to 12V converter” to the power/camera harness. Make sure that the 24V to 12V ...
    • Gen3_ITC - General - What is a GEN 3 ITC?

      This system has been designed specifically for use with Integrated Tool Carriers (ITC) to cover all relative national and international safety standards. This Tech Doc details system specifications, system functionality, installation requirements, ...