Gen3_ITC - Installation - Volvo L120H & L90 Machine Connections

This Tech Doc describes how to connect the safety systems to the existing electronics in the machine

To complete all of the steps within this Tech Doc, you should either be an auto electrician or have the services of an auto electrician.
EQSS accepts no responsibility for ultimate wiring outcomes by unqualified personnel
Installation Steps:
1. Route both the system power for
the 24V to 12V converter and the
DT6 connection cable from the
remote camera switch as shown in
the diagram below.
2. Locate the system power lug - 24V (near the right side of ECU).
Attach the power wire (yellow)
from the 24V to 12V converter to
the ring lug.
3. Locate the system ground lug
near the right side of ECU.
Attach the ground wire (black)
from the 24V to 12V converter to
the ring lug.
4. Locate the terminal DC2 in main
ECU near the top of the board.
Cut and Splice the wire attached
to the terminal with the ‘24V to
12V converter’ signal wire
(Purple).
5. Locate the terminal DB6 in main
ECU near the top of the board.
Cut and Splice the wire attached
to the terminal with the Reverse
Camera signal wire (White).

Some machines had wiring modifications applied by the end user and may not match the wiring in this Tech Doc

Isolate the main battery before starting the machine
connections

After completing the machine connections the boom can not
be moved until the installation is complete
Related Articles
Gen3_ITC - Installation - Caterpillar 962K Machine Connections
This Tech Doc describes how to connect the safety systems to the existing electronics in the machine Installation Steps: 1. Locate the system power lug (Constant 24V). Attach the power wire (yellow) from the 24V to 12V converter to the ring lug. 2. ...
Gen3 - Installation - Generic Machine Electrical Connections
To accommodate the various brands and many models, a substantial number of Gen 3 installation kits have been engineered and are available for purchase from EQSS. The following sections serve to illustrate common electrical connections from the Gen 3 ...
Gen3_ITC - Installation - Volvo L120H Main Head & Rod Pressure Sensors
The hydraulic pressure sensors are used to measure the lifting load of the ITC Installation Steps: Completely lower the boom. Apply the handbrake and insert chock under wheels. Once lowered, release any residual pressure by pulling on the manual ...
Gen4 - Installation - Haulotte HTL 4014 Machine Connections
The following procedures connect the safety systems to the existing electronics in the machine Installation Steps: 1. Isolate the machine before continuing to avoid damage to the electronic modules. 2. Locate the connector CN08 which can be found ...
Gen4 - Installation - Haulotte HTL 4017 Machine Connections
The following procedures connect the safety systems to the existing electronics in the machine Installation Steps: 1. Isolate the machine before continuing to avoid damage to the electronic modules. 2. Locate the connector CN08 which can be found ...